Dept. of Trans. PROGRESS Serial No. Contract No. 22-055-12-02 01-488024 PROGRESS PAYMENT VOUCHER %complete: %time: 3% 41% Location: Federal Project: 01-DN-199-1.1/2.6 NONE Progress payment No. 002 Payment period ending: 02-20-22 PACIFIC EARTHSCAPE 1225 CENTRAL AVE #11 MCKINLEYVILLE CA 95519 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 67,751.20 7,960.70 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 67,751.20 7,960.70 5. Mobilization 6. Total Work Completed 67,751.20 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 67,751.20 7,960.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 7,960.70