Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 10-344-11-36 01-488504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 01-VAR Federal Project: NONE Progress payment No. 02 Payment period ending: 11-06-10 PETERSON CHASE GENERAL ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 92614 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 169,378.75 34,124.00 2.a. Extra Work 5,745.65 5,745.65 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 175,124.40 39,869.65 5. Mobilization 21,000.00 0.00 6. Total Work Completed 196,124.40 7. Deductions -9,500.00 -7,287.85 8. a.Contract Retentions b. Unsatisfactory Prog. 0.00 13,525.48 c. Reduction after 95% Comp. 9. Total pay to Contractor 186,624.40 46,107.28 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 46,107.28