Dept. of Trans. PROGRESS Serial No. Contract No. 11-265-09-25 01-489004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 60% 55% 01-DN-199-33.5/33.9 Federal Project: NONE Progress payment No. 04 Payment period ending: 09-20-11 ASHRON CONSTRUCTION AND RESTORATION INC 1109 N FAIR OAKS AVE SUNNYVALE CA 94089 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 443,829.09 82,385.67 2.a. Extra Work 47,189.06 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 491,018.15 82,385.67 5. Mobilization 58,616.00 2,930.80 6. Total Work Completed 549,634.15 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 549,634.15 85,316.47 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 85,316.47