Dept. of Trans. FINAL Serial No. Contract No. 11-195-09-50 01-496004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 01-HUM-101-121.8/122.7 Federal Project: HSNH-Q101(195) G-Q101(195) Progress payment No. 03 Payment period ending: 04-06-11 APEX FENCE CO INC P O BOX 545 ANDERSON CA 96007 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 176,132.50 0.00 2.a. Extra Work 7,281.11 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 183,413.61 0.00 5. Mobilization 6. Total Work Completed 183,413.61 7. Deductions 0.00 11,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 183,413.61 11,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 11,000.00