Dept. of Trans. PROGRESS Serial No. Contract No. 16-113-12-04 01-497714 PROGRESS PAYMENT VOUCHER %complete: %time: 28% 17% Location: Federal Project: 01-MEN-1-2.3/2.5 STP-P001(604) Progress payment No. 001 Payment period ending: 04-20-16 GRANITE CONSTRUCTION COMPANY 1324 SOUTH STATE ST UKIAH CA 95482 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 160,289.74 160,289.74 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 160,289.74 160,289.74 5. Mobilization 58,162.80 58,162.80 6. Total Work Completed 218,452.54 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 218,452.54 218,452.54 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 218,452.54