Dept. of Trans. PROGRESS Serial No. Contract No. 16-173-13-26 01-497714 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 52% Location: Federal Project: 01-MEN-1-2.3/2.5 STP-P001(604) Progress payment No. 003 Payment period ending: 06-20-16 GRANITE CONSTRUCTION COMPANY 1324 SOUTH STATE ST UKIAH CA 95482 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 647,102.07 272,396.41 2. a. Extra Work 70,418.01 33,414.63 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 717,520.08 305,811.04 5. Mobilization 61,224.00 0.00 6. Total Work Completed 778,744.08 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 778,744.08 305,811.04 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 305,811.04