Dept. of Trans. PROGRESS Serial No. Contract No. 12-356-09-12 01-499404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 56% 60% 01-DN-101-R4.4/12.6 Federal Project: NONE Progress payment No. 03 Payment period ending: 12-19-12 TIDEWATER CONTRACTORS, INC P O BOX 1956 BROOKINGS, OR 97415 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 53,192.80 8,243.00 2.a. Extra Work 787,927.23 233,869.71 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 841,120.03 242,112.71 5. Mobilization 6. Total Work Completed 841,120.03 7. Deductions -6,390.51 -6,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 834,729.52 236,112.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 236,112.71