Dept. of Trans. PROGRESS Serial No. Contract No. 11-269-10-32 01-499804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 63% 74% 01-HUM-254-0.0/10.8 Federal Project: NONE Progress payment No. 02 Payment period ending: 09-20-11 ADVANTAGE PAVING AND EXCAVATING INC P O BOX 302 YREKA CA 96097 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 409,257.94 231,620.04 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 409,257.94 231,620.04 5. Mobilization 6. Total Work Completed 409,257.94 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 409,257.94 231,620.04 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 231,620.04