Dept. of Trans. PROGRESS Serial No. Contract No. 05-263-10-18 02-0C0504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 89% 96% 02-PLU-70-50.0/51.6 Federal Project: NONE Progress payment No. 04 Payment period ending: 09-20-05 ROYAL ELECTRIC COMPANY P O BOX 231430 SACRAMENTO CA 958230407 Escrow No. 02198 Total Estimate This Estimate 1. Contract Itms Without Mobil. 832,825.03 455,227.39 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 832,825.03 455,227.39 5. Mobilization 6. Total Work Completed 832,825.03 7. Deductions -2,000.00 -1,000.00 8. a.Contract Retentions -41,641.25 -22,761.37 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 789,183.78 431,466.02 10. Reduction Amt to Escrow 11. Payment to Escrow 41,640.00 12. Net Pymt. this Estimate 431,466.02