Dept. of Trans. PROGRESS Serial No. Contract No. 08-326-15-07 02-0C3304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 87% 82% 02-SIS-5-R7.2/ .0 Federal Project: NONE Progress payment No. 06 Payment period ending: 11-20-08 TIMBERWORKS P O BOX 1240 MOUNT SHASTA CA 96067 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 812,556.40 135,522.71 2.a. Extra Work 2,935.66 2,935.66 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 815,492.06 138,458.37 5. Mobilization 6. Total Work Completed 815,492.06 7. Deductions 8. a.Contract Retentions -40,774.60 -6,922.92 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 774,717.46 131,535.45 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 131,535.45