Dept. of Trans. PROGRESS Serial No. Contract No. 11-112-08-13 02-0C5904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 10% 3% 02-SHA-5-R3.0/R19.0 Federal Project: NHS Progress payment No. 03 Payment period ending: 04-20-11 ROADWAY ELECTRICAL WORKS INCORPORATED 3442 6TH STREET CERES CA 95307 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 152,348.45 151,523.45 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 352,301.29 213,776.36 4. Earned Subject to Retention 504,649.74 365,299.81 5. Mobilization 260,149.65 260,149.65 6. Total Work Completed 412,498.10 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 764,799.39 625,449.46 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 625,449.46