Dept. of Trans. PROGRESS Serial No. Contract No. 11-235-14-12 02-0C5904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 71% 74% 02-SHA-5-R3.0/R19.0 Federal Project: NHS Progress payment No. 07 Payment period ending: 08-19-11 ROADWAY ENGINEERING WORKS INC 3442 6TH STREET CERES CA 95307 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,541,689.99 433,475.86 2.a. Extra Work 17,659.64 0.00 b. Adjustment Comp. 3. Materials on Hand 161,978.71 0.00 4. Earned Subject to Retention 2,721,328.34 433,475.86 5. Mobilization 346,866.20 0.00 6. Total Work Completed 2,906,215.83 7. Deductions -4,000.00 -2,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,064,194.54 431,475.86 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 431,475.86