Dept. of Trans. PROGRESS Serial No. Contract No. 06-207-08-35 02-0C9104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 41% 65% 02-TRI-299-20.9/21.4 Federal Project: NONE Progress payment No. 03 Payment period ending: 07-20-06 R BROWN CONSTRUCTION COMPANY INC P O BOX 406 WILLOW CREEK CA 95573 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 372,946.43 88,330.00 2.a. Extra Work 10,086.81 10,086.81 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 383,033.24 98,416.81 5. Mobilization 95,000.00 0.00 6. Total Work Completed 478,033.24 7. Deductions 8. a.Contract Retentions -21,415.00 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 456,618.24 98,416.81 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 98,416.81