Dept. of Trans. PROGRESS Serial No. Contract No. 17-202-15-04 02-0E0904 PROGRESS PAYMENT VOUCHER %complete: %time: 59% 45% Location: Federal Project: 02-SHA-5-0.1 NHPI-005 8-355(E) Progress payment No. 017 Payment period ending: 07-20-17 GOLDEN STATE BRIDGE INC 3701 MALLARD DR BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,965,673.85 944,087.70 2. a. Extra Work 350,477.38 24,421.12 b. Adustment Comp. 3. Materials on Hand 109,144.26 0.00 4. Earned Subject to Retention 13,425,295.49 968,508.82 5. Mobilization 2,222,222.00 111,111.10 6. Total Work Completed 15,538,373.23 7. Deductions -1,000.00 -1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 15,646,517.49 1,078,619.92 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,078,619.92