Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 20-056-09-33 02-0E0904 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 02-SHA-5-0.1 NHPI-005 8-355(E) Progress payment No. 051 Payment period ending: 01-23-20 GOLDEN STATE BRIDGE INC 3701 MALLARD DR BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 23,752,460.59 -81,194.50 2. a. Extra Work 5,328,646.01 112,196.95 b. Adustment Comp. -20,895.24 0.00 3. Materials on Hand 4. Earned Subject to Retention 29,060,211.36 31,002.45 5. Mobilization 2,222,222.00 0.00 6. Total Work Completed 31,282,433.36 7. Deductions -42,000.00 -42,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 31,240,433.36 -10,997.55 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -10,997.55