Dept. of Trans. SEMI-FINAL Serial No. Contract No. 09-014-17-02 02-0E1504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 02-TRI-299-18.7/18.9 Federal Project: NONE Progress payment No. 04 Payment period ending: 11-18-08 R BROWN CONSTRUCTION COMPANY INC P O BOX 406 WILLOW CREEK CA 95573 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 528,474.67 7,910.88 2.a. Extra Work 78,667.66 11,885.37 b. Adjustment Comp. -2,037.19 -2,037.19 3. Materials on Hand 4. Earned Subject to Retention 605,105.14 17,759.06 5. Mobilization 6. Total Work Completed 605,105.14 7. Deductions 0.00 5,948.34 8. a.Contract Retentions -26,159.54 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 26,159.54 0.00 9. Total pay to Contractor 605,105.14 23,707.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 23,707.40