Dept. of Trans. PROGRESS Serial No. Contract No. 18-143-08-58 02-0E1804 PROGRESS PAYMENT VOUCHER %complete: %time: 11% 17% Location: Federal Project: 02-PLU-89-30.2/30.5 ACST-P089(121) Progress payment No. 002 Payment period ending: 05-20-18 Q & D CONSTRUCTION INC 1050 S 21ST ST SPARKS NV 89431 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 592,452.75 536,222.75 2. a. Extra Work 1,300.00 1,300.00 b. Adustment Comp. 3. Materials on Hand 26,119.00 26,119.00 4. Earned Subject to Retention 619,871.75 563,641.75 5. Mobilization 285,000.00 285,000.00 6. Total Work Completed 878,752.75 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 904,871.75 848,641.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 848,641.75