Dept. of Trans. SEMI-FINAL Serial No. Contract No. 09-337-14-16 02-0E4804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 02-SIS-5-58.1/69.3 Federal Project: NONE Progress payment No. 10 Payment period ending: 08-17-09 J F SHEA CONSTRUCTION INC P O BOX 494519 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,201,570.59 0.00 2.a. Extra Work 18,876.90 8,465.94 b. Adjustment Comp. -82,822.10 0.00 3. Materials on Hand 4. Earned Subject to Retention 5,137,625.39 8,465.94 5. Mobilization 200,000.00 0.00 6. Total Work Completed 5,337,625.39 7. Deductions -14,000.00 0.00 8. a.Contract Retentions -242,677.59 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 242,677.59 0.00 9. Total pay to Contractor 5,323,625.39 8,465.94 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 8,465.94