Dept. of Trans. SEMI-FINAL Serial No. Contract No. 09-155-14-29 02-0E6204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 02-SIE-395-0.0/3.1 Federal Project: NONE Progress payment No. 03 Payment period ending: 05-14-09 SIERRA NEVADA CONSTRUCTION INC P O BOX 50760 SPARKS NV 89435 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 560,046.50 0.00 2.a. Extra Work 49,446.00 0.00 b. Adjustment Comp. -48,755.40 4,690.20 3. Materials on Hand 4. Earned Subject to Retention 560,737.10 4,690.20 5. Mobilization 6. Total Work Completed 560,737.10 7. Deductions -1,000.00 0.00 8. a.Contract Retentions -2,582.00 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 2,582.00 0.00 9. Total pay to Contractor 559,737.10 4,690.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,690.20