Dept. of Trans. SEMI-FINAL Serial No. Contract No. 11-230-13-07 02-0E8004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 02-TEH-5-9.5/10.5 Federal Project: NONE Progress payment No. 09 Payment period ending: 04-14-11 AMERICAN CONTRACTORS INDEMNITY COMPANY 601 S. FIGUEROA STREET, #1600 LOS ANGELES, CA 90017 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 591,984.18 818.79 2.a. Extra Work 47,148.64 15,599.00 b. Adjustment Comp. -1,907.06 -1,907.06 3. Materials on Hand 4. Earned Subject to Retention 637,225.76 14,510.73 5. Mobilization 6. Total Work Completed 637,225.76 7. Deductions -2,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 635,225.76 14,510.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 14,510.73