Dept. of Trans. PROGRESS Serial No. Contract No. 09-239-07-25 02-0E8304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 41% 63% 02-LAS-139-7.2/R7.5 Federal Project: NONE Progress payment No. 01 Payment period ending: 08-20-09 STEVE MANNING CONSTRUCTION INC P O BOX 491660 REDDING CA 96002 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 242,129.00 242,129.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 242,129.00 242,129.00 5. Mobilization 6. Total Work Completed 242,129.00 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 242,129.00 242,129.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 242,129.00