Dept. of Trans. PROGRESS Serial No. Contract No. 13-142-11-43 02-0E8404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 27% 36% 02-SIS-3-47.7/48.5 Federal Project: NONE Progress payment No. 02 Payment period ending: 05-20-13 CUSTOM CRUSHING INDUSTRIES INC P O BOX 357 GRENADA CA 96038 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 201,249.17 189,624.17 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 201,249.17 189,624.17 5. Mobilization 6. Total Work Completed 201,249.17 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 201,249.17 189,624.17 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 189,624.17