Dept. of Trans. PROGRESS Serial No. Contract No. 14-141-13-12 02-0H0404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 34% 50% 02-SHA-5-13.8/14.1 Federal Project: NONE Progress payment No. 04 Payment period ending: 04-18-14 SHASTA CONSTRUCTORS, INC. 4150 FIG TREE LANE REDDING, CA 96002 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2.a. Extra Work 269,417.38 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 269,417.38 0.00 5. Mobilization 6. Total Work Completed 269,417.38 7. Deductions 0.00 11,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 269,417.38 11,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 11,000.00