Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 15-308-13-50 02-0H3004 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 02-SHA-44-R14.4/34.0 STPN-P044(52) Progress payment No. 003 Payment period ending: 09-25-15 J.F. SHEA CONSTRUCTION, INC. P.O. BOX 494519 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,226,598.59 -7,551.33 2. a. Extra Work 35,757.40 35,757.40 b. Adustment Comp. 77,331.70 77,331.70 3. Materials on Hand 4. Earned Subject to Retention 3,339,687.69 105,537.77 5. Mobilization 6. Total Work Completed 3,339,687.69 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,329,687.69 95,537.77 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 95,537.77