Dept. of Trans. PROGRESS Serial No. Contract No. 15-111-11-45 02-0H5304 PROGRESS PAYMENT VOUCHER %complete: %time: 64% 100% Location: Federal Project: 02-VAR NONE Progress payment No. 006 Payment period ending: 04-20-15 STEWART ENGINEERING, INC. P.O. BOX 990010 REDDING, CA 96099 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 471,518.22 67,642.81 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 471,518.22 67,642.81 5. Mobilization 6. Total Work Completed 471,518.22 7. Deductions -8,000.00 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 463,518.22 62,642.81 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 62,642.81