Dept. of Trans. PROGRESS Serial No. Contract No. 16-025-15-10 02-0H7104 PROGRESS PAYMENT VOUCHER %complete: %time: 87% 95% Location: Federal Project: 02-LAS-395-49.5/49.6 NONE Progress payment No. 008 Payment period ending: 01-20-16 STEWART ENGINEERING, INC. P.O. BOX 990010 REDDING, CA 96099 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 455,560.90 43,202.47 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 455,560.90 43,202.47 5. Mobilization 6. Total Work Completed 455,560.90 7. Deductions -1,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 454,560.90 43,202.47 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 43,202.47