Dept. of Trans. PROGRESS Serial No. Contract No. 19-199-14-29 02-0H7604 PROGRESS PAYMENT VOUCHER %complete: %time: 12% 32% Location: Federal Project: 02-LAS-70-0.0/3.9 B1NH-P070(138) 02-PLU-70-90.3/95.9 Progress payment No. 003 Payment period ending: 07-20-19 HAT CREEK CONSTRUCTION & MATERIALS INC 24339 STATE HWY 89 N BURNEY CA 96013 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,493,944.53 617,993.50 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 0.00 -21,177.00 4. Earned Subject to Retention 1,493,944.53 596,816.50 5. Mobilization 750,199.88 0.00 6. Total Work Completed 2,244,144.41 7. Deductions -3,000.00 -3,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,241,144.41 593,816.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 593,816.50