Dept. of Trans. PROGRESS Serial No. Contract No. 19-260-11-08 02-0H8004 PROGRESS PAYMENT VOUCHER %complete: %time: 25% 14% Location: Federal Project: 02-PLU-70-31.8/31.8 NONE Progress payment No. 002 Payment period ending: 09-20-19 PACIFIC EARTHSCAPE 1225 CENTRAL AVE #11 MCKINLEYVILLE CA 95519 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 216,793.20 33,333.30 2. a. Extra Work 16,112.75 12,090.05 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 232,905.95 45,423.35 5. Mobilization 73,150.00 15,400.00 6. Total Work Completed 306,055.95 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 306,055.95 60,823.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 60,823.35