Dept. of Trans. PROGRESS Serial No. Contract No. 20-199-14-04 02-0H8004 PROGRESS PAYMENT VOUCHER %complete: %time: 55% 51% Location: Federal Project: 02-PLU-70-31.8/31.8 NONE Progress payment No. 004 Payment period ending: 07-20-20 PACIFIC EARTHSCAPE 1225 CENTRAL AVE #11 MCKINLEYVILLE CA 95519 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 578,011.51 298,528.93 2. a. Extra Work 19,312.75 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 597,324.26 298,528.93 5. Mobilization 77,000.00 3,850.00 6. Total Work Completed 674,324.26 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 674,324.26 302,378.93 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 302,378.93