Dept. of Trans. PROGRESS Serial No. Contract No. 20-184-13-13 02-0J1704 PROGRESS PAYMENT VOUCHER %complete: %time: 27% 25% Location: Federal Project: 02-SIS-3-36.0/R46.9 NONE Progress payment No. 001 Payment period ending: 06-20-20 NORTHWEST PAVING INC 8115 SECLUDED VALLEY DRIVE REDDING CA 96001 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 193,321.25 193,321.25 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 193,321.25 193,321.25 5. Mobilization 6. Total Work Completed 193,321.25 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 193,321.25 193,321.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 193,321.25