Dept. of Trans. PROGRESS Serial No. Contract No. 23-201-09-12 02-0J5004 PROGRESS PAYMENT VOUCHER %complete: %time: 15% 22% Location: Federal Project: 02-TRI-3-25.0/25.2 NONE Progress payment No. 002 Payment period ending: 07-20-23 PACIFIC EARTHSCAPE 1225 CENTRAL AVE #11 MCKINLEYVILLE CA 95519 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 206,813.70 206,813.70 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 377,122.85 0.00 4. Earned Subject to Retention 583,936.55 206,813.70 5. Mobilization 147,410.55 31,033.80 6. Total Work Completed 354,224.25 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 731,347.10 237,847.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 237,847.50