Dept. of Trans. PROGRESS Serial No. Contract No. 23-263-12-39 02-0J5004 PROGRESS PAYMENT VOUCHER %complete: %time: 65% 63% Location: Federal Project: 02-TRI-3-25.0/25.2 NONE Progress payment No. 004 Payment period ending: 09-20-23 PACIFIC EARTHSCAPE 1225 CENTRAL AVE #11 MCKINLEYVILLE CA 95519 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,395,973.85 891,831.25 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 0.00 -377,122.85 4. Earned Subject to Retention 1,395,973.85 514,708.40 5. Mobilization 155,169.00 7,758.45 6. Total Work Completed 1,551,142.85 7. Deductions 0.00 6,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,551,142.85 528,466.85 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 528,466.85