Dept. of Trans. PROGRESS Serial No. Contract No. 20-301-10-54 02-0J7204 PROGRESS PAYMENT VOUCHER %complete: %time: 83% 100% Location: Federal Project: 02-SIS-96-369.0/37.2 NONE Progress payment No. 019 Payment period ending: 10-20-20 R BROWN CONSTRUCTION CO INC PO BOX 406 WILLOW CREEK CA 95573 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 10,926,585.53 805,731.90 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 10,926,585.53 805,731.90 5. Mobilization 6. Total Work Completed 10,926,585.53 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,926,585.53 805,731.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 805,731.90