Dept. of Trans. PROGRESS Serial No. Contract No. 24-260-14-43 02-0K3904 PROGRESS PAYMENT VOUCHER %complete: %time: 85% 10% Location: Federal Project: 02-VAR NONE Progress payment No. 001 Payment period ending: 09-20-24 HIGHWAY SPECIALTY COMPANY INC PO BOX 141 PALO CEDRO CA 96073 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 156,296.70 156,296.70 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 156,296.70 156,296.70 5. Mobilization 20,000.00 20,000.00 6. Total Work Completed 176,296.70 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 176,296.70 176,296.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 176,296.70