Dept. of Trans. PROGRESS Serial No. Contract No. 09-204-07-56 02-1C16A4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 37% 15% 02-SHA-299-5.4/5.8 Federal Project: ACST-P299(153) PH-P299(153) Progress payment No. 01 Payment period ending: 07-20-09 J F SHEA CONSTRUCTION INC P O BOX 494519 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 398,315.70 398,315.70 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 398,315.70 398,315.70 5. Mobilization 59,850.00 59,850.00 6. Total Work Completed 458,165.70 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 458,165.70 458,165.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 458,165.70