Dept. of Trans. PROGRESS Serial No. Contract No. 06-081-10-04 02-1C2104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 34% 60% 02-SIS-5-R40.1/R44.3 Federal Project: ACST-005-9(165) PEI-005-9(165) Progress payment No. 03 Payment period ending: 03-20-06 CUSTOM FENCE CO 293 NORTH 650 WEST KAYSVILLE UT 84037 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 147,677.30 5,045.40 2.a. Extra Work 23,040.00 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 170,717.30 5,045.40 5. Mobilization 6. Total Work Completed 170,717.30 7. Deductions -2,402.30 -2,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 168,315.00 3,045.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,045.40