Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 06-333-15-42 02-1C45U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 02-TEH-5-R27.3/R27.8 Federal Project: NONE Progress payment No. 05 Payment period ending: 11-15-06 AUBURN GARDENING AND LANDSCAPE P O BOX 2080 POLLOCK PINES CA 95726 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 472,011.98 98,914.98 2.a. Extra Work b. Adjustment Comp. -42,000.00 -42,000.00 3. Materials on Hand 4. Earned Subject to Retention 430,011.98 56,914.98 5. Mobilization 30,000.00 0.00 6. Total Work Completed 460,011.98 7. Deductions -19,891.49 -19,891.49 8. a.Contract Retentions -18,654.85 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 18,654.85 18,654.85 9. Total pay to Contractor 440,120.49 55,678.34 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 55,678.34