Dept. of Trans. PROGRESS Serial No. Contract No. 06-235-08-34 02-1C6904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 50% 84% 02-LAS-139-R25.0/52.0 Federal Project: NONE Progress payment No. 01 Payment period ending: 08-18-06 LARRANAGA CONSTRUCTION INC P O BOX 1604 ALTURAS CA 96101 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 369,241.60 369,241.60 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 369,241.60 369,241.60 5. Mobilization 6. Total Work Completed 369,241.60 7. Deductions 8. a.Contract Retentions -18,462.08 -18,462.08 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 350,779.52 350,779.52 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 350,779.52