Dept. of Trans. PROGRESS Serial No. Contract No. 18-114-14-38 02-1C7504 PROGRESS PAYMENT VOUCHER %complete: %time: 3% 2% Location: Federal Project: 02-PLU-70-14.9 ACST-P070(133) Progress payment No. 003 Payment period ending: 04-20-18 STEWART ENGINEERING INC PO BOX 990010 REDDING CA 96099 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 334,491.70 263,086.10 2. a. Extra Work 13,666.13 10,317.80 b. Adustment Comp. 3. Materials on Hand 18,407.00 18,407.00 4. Earned Subject to Retention 366,564.83 291,810.90 5. Mobilization 6. Total Work Completed 348,157.83 7. Deductions 0.00 2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 366,564.83 293,810.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 293,810.90