Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 06-270-17-20 02-1C8104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 02-TRI-299-37.0/41.5 Federal Project: NONE Progress payment No. 03 Payment period ending: 08-08-06 STEVE MANNING CONSTRUCTION INC P O BOX 491660 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 697,228.07 0.00 2.a. Extra Work 23,571.74 23,571.74 b. Adjustment Comp. 654.77 654.77 3. Materials on Hand 4. Earned Subject to Retention 721,454.58 24,226.51 5. Mobilization 6. Total Work Completed 721,454.58 7. Deductions -2,000.00 18,000.00 8. a.Contract Retentions -33,219.83 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 33,219.83 0.00 9. Total pay to Contractor 719,454.58 42,226.51 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 42,226.51