Dept. of Trans. PROGRESS Serial No. Contract No. 06-202-15-10 02-1C8304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 51% 80% 02-MOD-139-33.5/40.6 Federal Project: NONE Progress payment No. 02 Payment period ending: 07-20-06 EAGLE PEAK ROCK AND PAVING INC P O BOX 879 ALTURAS CA 96101 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 799,646.20 797,021.20 2.a. Extra Work b. Adjustment Comp. 3,800.00 3,800.00 3. Materials on Hand 4. Earned Subject to Retention 803,446.20 800,821.20 5. Mobilization 6. Total Work Completed 803,446.20 7. Deductions 8. a.Contract Retentions -40,172.31 -39,909.81 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 763,273.89 760,911.39 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 760,911.39