Dept. of Trans. PROGRESS Serial No. Contract No. 05-266-12-11 02-1C8904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 97% 97% 02-SIS-3-26.9/R46.9 Federal Project: NONE Progress payment No. 02 Payment period ending: 09-20-05 NORTHERN CALIFORNIA PAVING P O BOX 1231 YREKA CA 96097 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 805,908.79 398,400.87 2.a. Extra Work 17,553.66 7,720.78 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 823,462.45 406,121.65 5. Mobilization 6. Total Work Completed 823,462.45 7. Deductions -5,000.00 -5,000.00 8. a.Contract Retentions -41,173.12 -20,306.08 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 777,289.33 380,815.57 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 380,815.57