Dept. of Trans. PROGRESS Serial No. Contract No. 06-114-12-34 02-1C9004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 95% 100% 02-SHA-44-R14.4/43.3 Federal Project: NONE Progress payment No. 08 Payment period ending: 04-20-06 INTERMOUNTAIN SLURRY SEAL INC P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,032,856.15 5,325.00 2.a. Extra Work 25,077.78 0.00 b. Adjustment Comp. -3,199.70 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,054,734.23 5,325.00 5. Mobilization 6. Total Work Completed 1,054,734.23 7. Deductions -26,500.00 0.00 8. a.Contract Retentions -52,736.71 -266.25 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 975,497.52 5,058.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,058.75