Dept. of Trans. SEMI-FINAL Serial No. Contract No. 11-209-16-10 02-1E3204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 02-MOD-395-0.0/R20.8 Federal Project: SARR-P395(224) A-P395(224) Progress payment No. 07 Payment period ending: 12-29-10 INTERNATIONAL SURFACING SYSTEMS P O BOX 4770 MODESTO CA 95352 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,822,723.16 0.00 2.a. Extra Work b. Adjustment Comp. -7,325.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,815,398.16 0.00 5. Mobilization 6. Total Work Completed 1,815,398.16 7. Deductions -14,000.00 20,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,801,398.16 20,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 20,000.00