Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 11-241-09-43 02-1E5804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 02-MOD-299-0.3/0.5 Federal Project: NONE Progress payment No. 01 Payment period ending: 08-19-11 HAT CREEK CONSTRUCTION AND MATERIALS INC 24339 HWY 89 N BURNEY CA 96013 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 279,935.24 279,935.24 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 279,935.24 279,935.24 5. Mobilization 6. Total Work Completed 279,935.24 7. Deductions -15,000.00 -15,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 264,935.24 264,935.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 264,935.24