Dept. of Trans. PROGRESS Serial No. Contract No. 12-065-15-54 02-1E8204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 73% 60% 02-TEH-36-85.8/87.5 Federal Project: STPP-360(91E) Progress payment No. 04 Payment period ending: 02-17-12 DIG IT CONSTRUCTION INC P O BOX 494 CHESTER CA 96020 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 461,434.85 1,243.38 2.a. Extra Work 54,536.37 25,268.72 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 515,971.22 26,512.10 5. Mobilization 6. Total Work Completed 515,971.22 7. Deductions -3,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 512,971.22 26,512.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 26,512.10