Dept. of Trans. PROGRESS Serial No. Contract No. 16-236-13-58 02-1H0104 PROGRESS PAYMENT VOUCHER %complete: %time: 37% 21% Location: Federal Project: 02-PLU-70-46.2/53.5 STPP-070(131) Progress payment No. 001 Payment period ending: 08-20-16 SIERRA NEVADA CONSTRUCTION INC 2055 E. GREG ST SPARKS NV 89431 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 775,773.62 775,773.62 2. a. Extra Work 37,000.00 37,000.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 812,773.62 812,773.62 5. Mobilization 6. Total Work Completed 812,773.62 7. Deductions -2,000.00 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 810,773.62 810,773.62 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 810,773.62