Dept. of Trans. PROGRESS Serial No. Contract No. 16-264-15-03 02-1H0504 PROGRESS PAYMENT VOUCHER %complete: %time: 86% 95% Location: Federal Project: 02-PLU-89-8.7/12.9 NONE Progress payment No. 002 Payment period ending: 09-20-16 DIG IT CONSTRUCTION INC. PO BOX 494 CHESTER CA 96020 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 946,143.15 679,697.03 2. a. Extra Work 22,349.51 22,349.51 b. Adustment Comp. 19,516.81 19,516.81 3. Materials on Hand 4. Earned Subject to Retention 988,009.47 721,563.35 5. Mobilization 6. Total Work Completed 988,009.47 7. Deductions -6,000.00 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 982,009.47 716,563.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 716,563.35