Dept. of Trans. PROGRESS Serial No. Contract No. 21-081-15-12 02-1H1104 PROGRESS PAYMENT VOUCHER %complete: %time: 76% 58% Location: Federal Project: 02-LAS-299-25.6/25.6 NONE Progress payment No. 013 Payment period ending: 03-20-21 WALSH CONSTRUCTION COMPANY II LLC 1390 WILLOW PASS RD #950 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,007,687.03 321,383.44 2. a. Extra Work 527,412.90 16,586.00 b. Adustment Comp. -21,146.42 0.00 3. Materials on Hand 4. Earned Subject to Retention 10,513,953.51 337,969.44 5. Mobilization 6. Total Work Completed 10,513,953.51 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,513,953.51 337,969.44 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 337,969.44