Dept. of Trans. PROGRESS Serial No. Contract No. 21-208-10-53 02-1H1104 PROGRESS PAYMENT VOUCHER %complete: %time: 91% 81% Location: Federal Project: 02-LAS-299-25.6/25.6 NONE Progress payment No. 017 Payment period ending: 07-20-21 WALSH CONSTRUCTION COMPANY II LLC 1390 WILLOW PASS RD #950 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,989,803.20 454,356.92 2. a. Extra Work 567,315.66 0.00 b. Adustment Comp. -5,974.42 0.00 3. Materials on Hand 4. Earned Subject to Retention 12,551,144.44 454,356.92 5. Mobilization 6. Total Work Completed 12,551,144.44 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 12,551,144.44 454,356.92 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 454,356.92